AGV Implementation Process

Step-by-step guide for AGV projects: From the first idea to productive operation – phases, milestones, and typical timeframes.

Reading time: 3 min

Project Phases Overview

An AGV implementation typically goes through five phases:

1

Analysis & Concept

2-4 weeks

2

RFQ & Vendor Selection

4-8 weeks

3

Detail Planning

4-8 weeks

4

Implementation & Commissioning

8-16 weeks

5

Ramp-up & Optimization

4-12 weeks

Total Duration: Typically 6-12 months from decision to full operation.

Phase 1: Analysis & Concept

Tasks

  • As-is analysis of current material flows
  • Goal definition (throughput, availability, costs)
  • Create rough layout
  • Feasibility check
  • Business case calculation

Deliverables

  • Requirements document / specification
  • Volume estimates
  • Go/No-Go decision
Invest sufficient time in this phase. Thorough analysis prevents expensive surprises later.

Phase 2: RFQ & Vendor Selection

Tasks

  • Finalize specification
  • Identify and contact vendors
  • Obtain and compare quotes
  • Conduct reference visits
  • Negotiations and contract signing

Evaluation Criteria

Criterion Weighting (Example)
Technical suitability 30%
Price / TCO 25%
References / Experience 20%
Service & Support 15%
Project management 10%

Phase 3: Detail Planning

Tasks

  • Create detailed design (with vendor)
  • Define travel paths and stations
  • Specify interfaces (WMS, PLC, etc.)
  • Develop safety concept
  • Plan infrastructure (floor, WiFi, charging)

Key Stakeholders

  • IT department (network, interfaces)
  • Safety team (risk assessment)
  • Works council (if applicable)
  • Facilities management (construction)

Phase 4: Implementation & Commissioning

Process

  1. Prepare infrastructure

    • Floor remediation (if needed)
    • Install reflectors / navigation aids
    • Set up charging stations
    • Configure network
  2. Deliver & set up vehicles

    • Delivery and assembly
    • Basic configuration
  3. Configure software

    • Install fleet control
    • Teach maps / routes
    • Connect interfaces
  4. Testing

    • Function test of individual vehicles
    • Integration test with peripherals
    • Load test under real conditions
  5. Acceptance

    • Formal acceptance per specification
    • Hand over documentation
    • Conduct training

Phase 5: Ramp-up & Optimization

Tasks

  • Gradual production start
  • Observation and fine-tuning
  • Route and parameter optimization
  • Training additional staff
  • Transition to regular operation
Plan for reduced operation during ramp-up. You won't achieve full productivity on day one.

Common Pitfalls

Problem Prevention
Underestimated floor issues Early floor analysis
WiFi problems Coverage measurement before start
Interface issues Early IT involvement
Acceptance problems Change management, communication
Unrealistic schedules Build in buffers

Conclusion

An AGV implementation is a complex project requiring careful planning. Take time for the analysis phase and work closely with all stakeholders.

From strategy to vendor selection.
Hands-on guidance from experienced AGV experts.